Electricity supply from the public grid and heat supply via district heating

Ford-Werke, Saarlouis, Germany

Goal

Development of an optimized supply concept

Partnership

Construction of a self-generation plant and integration into the Saar district heating network

  • CHP plant with 22 MWel and 20 MWth
  • Operation of the generation plants by Iqony

Results

  • Investment: € 23 million
  • CO2 savings: 28,000 t/a

Impact

Improving the environmental balance, reducing costs, strengthening the plant location

 

Solutions for industry

Project facts

Generation
  • Electricity: 149,000 MWh/a
  • Heat: 138,000 MWh/a